Ellendale hosting restoration to 65-75% by end of May 2024
Company: Applied Digital - Project: Ellendale
What the later record shows
Delivered; the record does not say when
Capacity rose from ~80 MW on April 28, 2024 to full 180 MW as of June 28, 2024, exceeding the 65%-75% target. Whether that range was hit by the end of May 2024 is not stated.
“The Ellendale facility is currently operating at approximately 80 MW and the Company expects to continue to ramp capacity ahead of the schedule”
2024-04-28 · Applied Digital 8-K filed 2024-04-29 View cached copy (2026-08-31)Live source ↗
“As of June 28, 2024, the upgrades to the Ellendale Facility’s equipment were completed, and the Ellendale Facility has been restored to full operating capacity at 180 MW.”
2024-07-01 · Applied Digital 8-K filed 2024-07-02 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The 180 MW Ellendale hosting facility, re-energized to ~14% (25 MW), targets operating capacity of approximately 65%-75% of full capacity by the end of May 2024 as new transformers are installed.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “the Ellendale facility will target operating capacity of approximately 65%-75% of full capacity by the end of May 2024”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The release states that the 180 MW Ellendale facility had been re-energized to about 14% (25 MW). It also says the facility targets 65%-75% of full capacity by the end of May 2024 as new transformers are received and installed.
Confirmed in the source:
- The Ellendale, North Dakota datacenter hosting facility is 180 MW
- The Ellendale facility had been re-energized to approximately 14% of its full capacity, or 25 MW
- The Ellendale facility targets operating capacity of approximately 65%-75% of full capacity by the end of May 2024
- The capacity target depends on new transformers being received and installed
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/94/applied-digital-reports-fiscal-third-quarter-2024-results/) in full (29,636 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “the Ellendale facility will target operating capacity of approximately 65%-75% of full capacity by the end of May 2024”
confirms Earnings Release
Quote: “the Ellendale facility will target operating capacity of approximately 65%-75% of full capacity by the end of May 2024”
confirms Applied Digital 8-K filed 2024-04-29
Quote: “The Ellendale facility is currently operating at approximately 80 MW and the Company expects to continue to ramp capacity ahead of the schedule”
confirms Applied Digital 8-K filed 2024-07-02
Quote: “As of June 28, 2024, the upgrades to the Ellendale Facility’s equipment were completed, and the Ellendale Facility has been restored to full operating capacity at 180 MW.”