jain.com

Ellendale full capacity online

Company: Applied Digital - Project: Ellendale

Subject kind
facility capacity
Statement date
2023-04-06
Promised by
2023-06-30
Promised amount
180.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

A July 24, 2023 release says full energization was completed, and the facility was fully operational as of August 31, 2023. No passage says whether it was done by the June 30, 2023 target.

“The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“As of August 31, 2023, the Company’s 106 MW facility in Jamestown, North Dakota and 180 MW facility in Ellendale, North Dakota were fully operational.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The company expects the remaining half of Ellendale's 180 MW capacity to be turned on by the end of June 2023.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “the rest to be turned on by the end of June”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The April 6, 2023 release says the company anticipated the first half of Ellendale's 180 MW capacity would be turned on by the end of April and the rest by the end of June. That matches the claim.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “the rest to be turned on by the end of June”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Applied Digital 10-Q filed 2023-10-10

Quote: “As of August 31, 2023, the Company’s 106 MW facility in Jamestown, North Dakota and 180 MW facility in Ellendale, North Dakota were fully operational.”

View cached copy (2026-08-31)Live source ↗

confirms Earnings Release

Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2023-04-06.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.