Ellendale, ND planned capacity
Company: Applied Digital - Project: Ellendale
The claim, verbatim
Ellendale, North Dakota facility has planned capacity of 180MW under a five-year ESA with a utility partner.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “Applied Digital's third co-hosting facility is in Ellendale, North Dakota with planned capacity of 180MW.”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The release states that Ellendale has a planned capacity of 180MW. It also says the company entered into a five-year ESA with a utility partner for that site.
Confirmed in the source:
- Applied Digital's Ellendale, North Dakota facility has a planned capacity of 180MW
- Applied Digital entered into a five-year Energy Services Agreement with a utility partner for the Ellendale site
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/49/applied-digital-reports-fiscal-second-quarter-2023/) in full (26,009 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “Applied Digital's third co-hosting facility is in Ellendale, North Dakota with planned capacity of 180MW.”
confirms Earnings Release
Quote: “Applied Digital’s third co-hosting facility is in Ellendale, North Dakota with planned capacity of 180MW.”