jain.com

Data Center Hosting North Dakota capacity

Company: Applied Digital

Subject kind
facility capacity
Statement date
2026-10-03
Promised amount
286.0 MW
Current status
stated

The claim, verbatim

Data Center Hosting operates 286 MW for bitcoin mining: 106 MW in Jamestown, ND and 180 MW in Ellendale, ND, both at full capacity as of May 31, 2026.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-03)Live source ↗

Quote: “the Company’s 106 MW facility in Jamestown, ND, and 180 MW facility in Ellendale, ND, were operating at full capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “the Company’s 106 MW facility in Jamestown, ND, and 180 MW facility in Ellendale, ND, were operating at full capacity”

View cached copy (2026-10-03)Live source ↗