Ellendale ND remaining capacity energization

Company: Applied Digital - Project: Ellendale

Subject kind
facility timeline
Statement date
2023-04-06
Promised by
2023-06-30
Promised amount
90.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

The full 180 MW Ellendale facility is later reported operating at full capacity, with FY2024 described as its first full year of operations. No passage dates when the remaining half was energized.

“built a hosting facility, and began energizing the site on March 4, 2023”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
“As of August 31, 2024, our 106 MW facility in Jamestown, North Dakota and our 180 MW facility in Ellendale, North Dakota are operating at full capacity.”
2024-10-09 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“specifically our 180 MW Data Center Hosting Facility in Ellendale, ND, which accounted for a $60.0 million increase in revenue as it was its first full year of operations”
2025-07-29 · Applied Digital 10-K filed 2025-07-30 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Applied Digital expects the remaining half of the Ellendale facility's 180MW capacity to be turned on by the end of June 2023.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-03)Live source ↗Archive.org ↗

Quote: “and the rest to be turned on by the end of June”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The April 6, 2023 release says the first half of Ellendale's 180MW capacity was expected online by end of April 2023 and the rest by end of June.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved October 3, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “and the rest to be turned on by the end of June”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Applied Digital 424B5 filed 2024-05-06

Quote: “built a hosting facility, and began energizing the site on March 4, 2023”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-K filed 2025-07-30

Quote: “specifically our 180 MW Data Center Hosting Facility in Ellendale, ND, which accounted for a $60.0 million increase in revenue as it was its first full year of operations”

View cached copy (2026-08-31)Live source ↗

confirms Earnings Release

Quote: “As of August 31, 2024, our 106 MW facility in Jamestown, North Dakota and our 180 MW facility in Ellendale, North Dakota are operating at full capacity.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

October 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-03 was the source's retrieval date; source published 2023-04-06.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.