Ellendale 100 MW HPC facility groundbreaking
Company: Applied Digital - Project: Ellendale
The claim, verbatim
The company broke ground on its first 100 MW liquid-cooled HPC facility, a 342,000-square-foot building in Ellendale, North Dakota.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 342,000-square-foot building will provide ultra-low cost and highly efficient liquid-cooled infrastructure”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The HPC hosting update states the groundbreaking, the 100 MW size, the Ellendale location, the 342,000-square-foot building and its liquid-cooled design.
Confirmed in the source:
- The company broke ground on its first 100 MW high-performance compute facility
- The facility is in Ellendale, North Dakota
- The building is 342,000 square feet
- The facility will provide liquid-cooled infrastructure
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/81/applied-digital-reports-fiscal-second-quarter-2024-results/) in full (25,989 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 342,000-square-foot building will provide ultra-low cost and highly efficient liquid-cooled infrastructure”