Ellendale ND facility first half energization

Company: Applied Digital - Project: Ellendale

Subject kind
facility timeline
Statement date
2023-04-06
Promised by
2023-04-30
Promised amount
90.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

Full energization of the 180 MW facility was reported complete by July 24, 2023, which includes the first half. When the first 90 MW came online is not stated.

“The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company anticipates the first half of the Ellendale facility's 180 MW capacity will be turned on by the end of April 2023.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release states that the first half of Ellendale's 180 MW capacity was anticipated to be turned on by the end of April. It was issued April 6, 2023, which fixes the year.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2023-04-06.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.