Ellendale ND facility first half energization
Company: Applied Digital - Project: Ellendale
What the later record shows
Delivered; the record does not say when
Full energization of the 180 MW facility was reported complete by July 24, 2023, which includes the first half. When the first 90 MW came online is not stated.
“The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Company anticipates the first half of the Ellendale facility's 180 MW capacity will be turned on by the end of April 2023.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states that the first half of Ellendale's 180 MW capacity was anticipated to be turned on by the end of April. It was issued April 6, 2023, which fixes the year.
Confirmed in the source:
- The Company anticipated the first half of the Ellendale facility's 180 MW capacity would be turned on by the end of April (2023, per the April 6, 2023 release date)
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”
confirms Earnings Release
Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”
confirms Earnings Release
Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”