Ellendale ND facility first half energization

Company: Applied Digital

Subject kind
facility timeline
Statement date
2026-09-29
Promised by
2023-04-30
Promised amount
90.0 MW
Current status
stated

The claim, verbatim

Company anticipates the first half of the Ellendale facility's 180 MW capacity will be turned on by the end of April 2023.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “The Company anticipates the first half of the facility’s 180-Megawatt (“MW”) capacity will be turned on by the end of April”