Ellendale ND 180MW energization by end of Feb 2023
Company: Applied Digital - Project: Ellendale
What the later record shows
Delivered late · happened March 4, 2023
Energization was promised before the end of February 2023. The company began energizing the site on March 4, 2023, a few days late, and announced it on March 7.
“On March 7, 2023, we announced the energizing of the 180 MW facility in Ellendale, ND.”
2023-04-05 · Applied Digital 10-Q filed 2023-04-06 View cached copy (2026-09-13)Live source ↗
“built a hosting facility, and began energizing the site on March 4, 2023.”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The 180MW Ellendale, North Dakota facility, which broke ground September 8, 2022, is under construction with energization expected before the end of February (end of fiscal Q3).
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “the Company is actively constructing buildings with energization expected before the end of February”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The Ellendale update gives the 180MW capacity, the September 8, 2022 groundbreaking, active construction and energization expected before the end of February. The highlights separately tie this to the end of fiscal Q3.
Confirmed in the source:
- The Ellendale, North Dakota facility has planned capacity of 180MW
- The Company broke ground on the Ellendale site on September 8, 2022
- Ellendale buildings are actively under construction
- Ellendale energization is expected before the end of February
- Ellendale is expected to be energized by the end of fiscal third quarter
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/49/applied-digital-reports-fiscal-second-quarter-2023/) in full (26,009 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “the Company is actively constructing buildings with energization expected before the end of February”
confirms Earnings Release
Quote: “the Company is actively constructing buildings with energization expected before the end of February.”
confirms Applied Digital 424B5 filed 2024-05-06
Quote: “built a hosting facility, and began energizing the site on March 4, 2023.”
confirms Applied Digital 10-Q filed 2023-04-06
Quote: “On March 7, 2023, we announced the energizing of the 180 MW facility in Ellendale, ND.”