Ellendale energization Q1 2023

Company: Applied Digital - Project: Ellendale

Subject kind
facility timeline
Statement date
2022-10-11
Promised by
2023-03-31
Current status
verified

What the later record shows

Delivered on time · happened March 4, 2023

Energization began on March 4, 2023, within the promised first calendar quarter of 2023. Full energization was completed later, by July 2023.

“On March 7, 2023, we announced the energizing of the 180 MW facility in Ellendale, ND.”
2023-04-05 · Applied Digital 10-Q filed 2023-04-06 View cached copy (2026-09-13)Live source ↗
“built a hosting facility, and began energizing the site on March 4, 2023.”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Energization of the Ellendale facility is expected in the first calendar quarter of 2023.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The Ellendale facility update states this expectation directly.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/42/applied-blockchain-reports-fiscal-first-quarter-2023/) in full (25,723 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023.”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023.”

View cached copy (2026-10-08)Live source ↗

confirms Applied Digital 424B5 filed 2024-05-06

Quote: “built a hosting facility, and began energizing the site on March 4, 2023.”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-Q filed 2023-04-06

Quote: “On March 7, 2023, we announced the energizing of the 180 MW facility in Ellendale, ND.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2022-10-11.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.