jain.com

Currently energized colocation capacity

Company: Core Scientific - Project: Marble

Subject kind
facility capacity
Statement date
2025-10-29
Promised amount
120.0 MW
Current status
stated

The claim, verbatim

Approximately 120+ MW energized across Denton and Marble sites

Source (primary)

core-scientific 8-K exhibit (ef20057996_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “~120+ MW Energized Across Denton & Marble Sites”

How we checked this

Checked on September 29, 2026. The cited source supports every part of this claim.

The presentation's construction progress slide states this directly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000114036125039864/ef20057996_ex99-1.htm) in full (11,284 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (ef20057996_ex99-1.htm)

Quote: “~120+ MW Energized Across Denton & Marble Sites”

View cached copy (2026-09-27)Live source ↗