jain.com

High-grade hyperscaler Delta Forge 1 lease

Company: Applied Digital - Project: Delta Forge 1

Subject kind
customer
Statement date
2026-09-25
Promised by
2028-06-30
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Signed two 15-year leases with three 5-year renewal options for 300 MW of critical IT load at Delta Forge 1 (delivery 1H 2027 to 1H 2028)

Source (primary)

Investor Presentation (IR page (ir.applieddigital.com), ir_presentation)
View cached copy (2026-09-25)Live source ↗Archive.org ↗

Quote: “U.S. Based High Investment Grade Hyperscaler - Signed two 15-year leases with three 5-year options for 2 buildings at Delta Forge 1, utilizing 300 MW of IT load”

How we checked this

Checked on September 27, 2026. The cited source supports every part of this claim.

The timeline, lease table and Delta Forge 1 page establish the lease count, options, 300 MW critical IT capacity and delivery window.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/_assets/_c3b095776b399204354d8f26dbb2553c/appliedblockchaininc/db/2905/27269/pdf/APLD_INV_June2026_Updated-compressed.pdf) in full (47,679 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “U.S. Based High Investment Grade Hyperscaler - Signed two 15-year leases with three 5-year options for 2 buildings at Delta Forge 1, utilizing 300 MW of IT load”