Ellendale 180MW facility full energization
Company: Applied Digital - Project: Ellendale
The claim, verbatim
Applied Digital successfully completed full energization of its Ellendale, North Dakota facility after initiating the process in early March 2023, six months after initial construction began.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The Ellendale facility update states the full energization and the early-March start. The year 2023 is clear from the release's date and reporting period rather than stated explicitly.
Confirmed in the source:
- Applied Digital completed full energization of its Ellendale, North Dakota facility
- The energization process was initiated in early March
- Energization came six months after initial construction began
- The March in question is 2023, given the July 2023 release covering the fiscal year ended May 31, 2023
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/66/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (23,127 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
confirms Earnings Release
Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
confirms Earnings Release
Quote: “The Company successfully completed the full energization of the facility”
confirms Earnings Release
Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began”
confirms Earnings Release
Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”