jain.com

Matagorda County

Project of Marathon Digital

Kind
datacenter
Location
Matagorda County, Texas
County
Matagorda
State/region
TX
Country
US
Status
announced as of September 19, 2026

Where it stands

In July 2026 MARA acquired the project company holding rights to a 1,200+ acre powered land site in Matagorda County, Texas, with a utility letter agreement for 2,000 MW, for up to $600 million in milestone payments. The 2 GW of capacity is still subject to ERCOT and interconnection approvals, and no tenant lease has been signed. Reporting through September 2026 gives no sign that construction has started. Management targets about 1 GW by October 2027 and 2 GW by April 2028.

2,000 MW planned

PhaseMWStatusDateSource
Phase 1 (~1 GW)1000planned2027-10-01MARA has said about 1 gigawatt could become available by October 2027, with the site potentially reaching 2 gigawatts by April 2028.
2026-09-11 View cached copy (2026-09-12)Live source ↗
Full build-out (2 GW)2000planned2028-04-01The site is expected to access up to 1 GW by October 2027 and 2 GW by April 2028, subject to approvals.
2026-09-14 View cached copy (2026-09-18)Live source ↗

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: September 19, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook--
Under construction--
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure2,000 MW2026-09-19Matagorda County data center project

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2026-07-08
Starwood Digital Ventures - jv partner source

Claims about this project

2026-07-08 - stated
2026-07-08 - stated
2026-07-08 - stated
2 GW grid capacity by April 2028 2.0 GW. Promised by 2028-04-01.
2026-07-08 - stated
1 GW grid capacity by October 2027 1.0 GW. Promised by 2027-10-01.
2026-07-09 - stated
Texas site 2 GW expansion timeline 2.0 GW. Promised by 2028-06-30.
2026-07-09 - stated
2026-07-09 - stated
Texas site 1 GW capacity timeline 1.0 GW. Promised by 2027-10-31.
2026-07-15 - stated
Texas site 1 GW power access by October 2027 1.0 GW. Promised by 2027-10-31.
2026-07-15 - stated
Texas site 2 GW power access by April 2028 2.0 GW. Promised by 2028-04-30.
2026-08-13 - stated
2026-08-18 - stated
2026-08-25 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-05 - stated
Texas facility 1 GW capacity target 1.0 GW. Promised by 2027-10-31.
2026-09-05 - stated
Texas site 2 GW power capacity by April 2028 2.0 GW. Promised by 2028-04-01.
2026-09-05 - stated
Texas site 1 GW power capacity by October 2027 1.0 GW. Promised by 2027-10-01.
2026-09-05 - stated
Texas facility 2 GW capacity target 2.0 GW. Promised by 2028-04-30.
2026-09-08 - stated
2026-09-08 - stated
2026-09-10 - stated
2026-09-11 - stated
Matagorda 2 gigawatt availability target 2.0 GW. Promised by 2028-04-30.
2026-09-11 - stated
Matagorda site reaches 2 gigawatts by April 2028 2.0 GW. Promised by 2028-04-30.
2026-09-11 - stated
2026-09-11 - stated
Matagorda 1 gigawatt availability target 1.0 GW. Promised by 2027-10-31.
2026-09-14 - stated
Texas site power capacity 1.0 GW. Promised by 2027-10-31.
2026-09-14 - stated
Texas site power capacity 2.0 GW. Promised by 2028-04-30.
2026-09-15 - stated
Texas site expansion to 2 GW grid capacity 2.0 GW. Promised by 2028-06-30.
2026-09-15 - stated
Texas site to reach 1 GW grid capacity 1.0 GW. Promised by 2027-10-31.
2026-09-19 - stated
2026-09-19 - stated