jain.com

Matagorda County data center project

Company: Marathon Digital - Project: Matagorda County

Subject kind
facility capacity
Statement date
2026-09-19
Promised amount
2000.0 MW
Current status
stated

The claim, verbatim

Marathon Digital has a Matagorda County project in Texas planned for up to two gigawatts of capacity

Source (primary)

MARA Stock Rose 14% Friday. JPMorgan and Morgan Stanley Still Don’t Agree. - TIKR.com (-, news_article)
View cached copy (2026-09-22)Live source ↗

Quote: “the Matagorda County project in Texas, planned for up to two gigawatts of capacity”

How we checked this

Checked on September 26, 2026. The cited source supports part of this claim, but not all of it.

The article ties the two-gigawatt Matagorda County project to MARA Holdings, but it never uses the name Marathon Digital or links that name to MARA Holdings.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/mara-stock-rose-14-friday-jpmorgan-and-morgan-stanley-still-dont-agree) in full (9,019 characters, retrieved September 22, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms MARA Stock Rose 14% Friday. JPMorgan and Morgan Stanley Still Don’t Agree. - TIKR.com

Quote: “the Matagorda County project in Texas, planned for up to two gigawatts of capacity”