Massena
Project of CleanSpark
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 50 MW | 2025-05-07 | Massena NY hosting agreement expiration |
| Contracted a customer is on the hook | 50 MW | 2024-10-03 | Bitcoin mining colocation capacity at Coinmint Massena facility |
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | -- |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2023-11-30
Coinmint - operator source
Claims about this project
2023-11-30 - stated
2023-11-30 - stated
Massena NY co-located capacity 50.0 MW.
2023-11-30 - stated
2023-11-30 - stated
2023-11-30 - stated
Coinmint co-location deployment 16400.0 units.
2023-11-30 - stated
2024-02-07 - stated
2024-05-08 - stated
Massena NY hosting partnership 50.0 MW.
2024-10-03 - delayed
Coinmint colocation agreement expiration. Promised by 2025-01-01.
2024-10-03 - stated
2024-12-02 - delayed
Coinmint co-location agreement termination. Promised by 2025-01-01.
2024-12-02 - stated
2024-12-02 - delayed
Coinmint hosting agreement termination. Promised by 2025-01-01.
2024-12-02 - delayed
Coinmint co-location hosting agreement termination. Promised by 2025-01-01.
2024-12-02 - delayed
Coinmint hosting agreement termination. Promised by 2025-01-01.
2025-02-05 - delayed
2025-05-07 - delayed
2025-11-24 - delayed
Massena NY mining operation closure. Promised by 2024-12-31.
2025-11-24 - delayed
Coinmint hosting agreement expiration. Promised by 2025-01-01.