jain.com

Massena NY hosting partnership

Company: CleanSpark - Project: Massena

Subject kind
partnership
Statement date
2024-05-08
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

CleanSpark has a partner in Massena, NY that hosts 50 MW of computing capacity

Source (primary)

CleanSpark 10-Q filed 2024-05-09 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We have a partner in Massena, NY that hosts 50 MW for us”

How we checked this

Checked on September 18, 2026. The cited source supports every part of this claim.

The filing states that an independent data center operation in Massena, NY hosts 50 MW for CleanSpark. The 50 MW figure is a measure of power capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017024056330/clsk-20240331.htm) in full (186,116 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-Q filed 2024-05-09

Quote: “We have a partner in Massena, NY that hosts 50 MW for us”

View cached copy (2026-08-31)Live source ↗