Ulysses Site

Project of Cipher Mining

Kind
datacenter
State/region
OH
Country
US
Status
announced as of February 23, 2026

Where it stands

Cipher Mining acquired the 200 MW Ulysses data center site in Ohio in December 2025, with power capacity secured from AEP Ohio and land options on about 195 acres. As of the February 2026 10-K, the site was expected to energize in the fourth quarter of 2027. The 10-K describes it as suited for HPC and does not mention any construction or operating capacity. The passages do not include any later update.

200 MW planned

PhaseMWStatusDateSource
Ulysses Site200plannedIn December 2025, we acquired a 200 MW data center site in Ohio, referred to as Ulysses (the “Ulysses Site”).
2026-02-23 View cached copy (2026-08-31)Live source ↗

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: February 23, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook--
Under construction--
Permitted--
Interconnect approved utility has agreed to deliver200 MW2026-02-23Ulysses 200 MW facility Q4 2027 energization
Interconnect requested in a queue, nothing approved--
Announced a press-release figure200 MW2026-08-03Ulysses 200 MW target energization Q4 2027

Claims about this project

2026-02-23 - stated
Ulysses energization target. Promised by 2027-12-31.
2026-02-23 - stated
Ulysses 200 MW facility Q4 2027 energization 200.0 MW. Promised by 2027-12-31.
2026-05-04 - stated
Ulysses Q4 2027 energization target. Promised by 2027-10-01.
2026-05-04 - stated
Ulysses gross capacity 200.0 MW. Promised by 2027-10-01.
2026-08-03 - stated