Ulysses 200 MW target energization Q4 2027

Company: Cipher Mining - Project: Ulysses Site

Subject kind
facility timeline
Statement date
2026-08-03
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Ulysses expected to energize 200 MW with target energization in Q4 2027

Source (primary)

cipher-mining 8-K exhibit (cipherdigital_businessup.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-02)Live source ↗

Quote: “2027 Q4 Target Energization 200 MW Gross Capacity”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document lists Ulysses with a 2027 Q4 target energization and 200 MW gross capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm) in full (22,200 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (cipherdigital_businessup.htm)

Quote: “2027 Q4 Target Energization 200 MW Gross Capacity”