NC-1 property purchase in Greensboro, North Carolina
Company: WhiteFiber
What the later record shows
Not a promise: a reported event · happened May 20, 2025
The claim reports a purchase that had already happened on May 20, 2025. The 10-K repeats that the property was bought on that date.
“On May 20, 2025, we purchased a former industrial/manufacturing building together with the underlying land outside of Greensboro, North Carolina, which we intend to retrofit”
2026-03-25 · WhiteFiber 10-K filed 2026-03-26 View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Purchased former industrial/manufacturing building and land in Greensboro, North Carolina to retrofit into HPC data center
Source (primary)
WhiteFiber S-1/A filed 2025-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “On May 20, 2025, we purchased a former industrial/manufacturing building together with the underlying land outside of Greensboro, North Carolina (the "Property"), which we intend to retrofit to create an HPC data center ("NC-1").”
How we checked this
Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.
The prospectus confirms the purchase of the building and land and the plan to retrofit it into an HPC data center, but it places the property outside of Greensboro rather than in the city.
Confirmed in the source:
- WhiteFiber purchased a former industrial/manufacturing building together with the underlying land (May 20, 2025)
- The company intends to retrofit the property into an HPC data center (NC-1)
- The property is in the Greensboro, North Carolina area
We could not confirm this from the cited source:
- That the NC-1 property is located in Greensboro itself; the filing describes it as outside of Greensboro, North Carolina
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025068434/ea0249945-03.htm) in full (841,778 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber S-1/A filed 2025-07-29
Quote: “On May 20, 2025, we purchased a former industrial/manufacturing building together with the underlying land outside of Greensboro, North Carolina (the "Property"), which we intend to retrofit to create an HPC data center ("NC-1").”