Not a promise: a reported event · happened May 20, 2025

The claim reports the NC-1 purchase as already done on May 20, 2025. Later filings confirm it.

“On May 20, 2025, the Company acquired the building and land, together with all the related improvements owned by Unifi Manufacturing, Inc.”
2026-08-11 · WhiteFiber 10-Q filed 2026-08-12 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Purchased former industrial/manufacturing building and underlying land outside Greensboro, North Carolina on May 20, 2025 to retrofit into HPC data center (NC-1)

Source (primary)

WhiteFiber S-1/A filed 2025-07-23 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “On May 20, 2025, we purchased a former industrial/manufacturing building together with the underlying land outside of Greensboro, North Carolina (the "Property"), which we intend to retrofit to create an HPC data center ("NC-1").”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The prospectus states the May 20, 2025 purchase of the building and land near Greensboro and the plan to retrofit it into the NC-1 HPC data center.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025066839/ea0249945-s1a1_white.htm) in full (824,020 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber S-1/A filed 2025-07-23

Quote: “On May 20, 2025, we purchased a former industrial/manufacturing building together with the underlying land outside of Greensboro, North Carolina (the "Property"), which we intend to retrofit to create an HPC data center ("NC-1").”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.