NC-1 potential maximum capacity projection
Company: WhiteFiber
The claim, verbatim
Management believes NC-1 may receive and support up to 200 MW gross capacity over extended period, subject to infrastructure upgrades
Source (primary)
WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “Management believes based upon its review of the site and a Duke Energy preliminary transmission study, that NC-1 may receive and support up to 200 MW (gross) of total electrical supply over an extended period of time, subject to infrastructure upgrades, such as developing new substations and other conditions.”
How we checked this
Checked on September 15, 2026. The cited source supports every part of this claim.
The filing states management's belief, based on a site review and a Duke Energy preliminary study, that NC-1 could support up to 200 MW gross over time, subject to infrastructure upgrades.
Confirmed in the source:
- Management believes NC-1 may receive and support up to 200 MW (gross) of total electrical supply
- This would occur over an extended period of time
- It is subject to infrastructure upgrades such as new substations and other conditions
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390026034341/ea0278305-10k_white.htm) in full (600,249 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber 10-K filed 2026-03-26
Quote: “Management believes based upon its review of the site and a Duke Energy preliminary transmission study, that NC-1 may receive and support up to 200 MW (gross) of total electrical supply over an extended period of time, subject to infrastructure upgrades, such as developing new substations and other conditions.”