NC-1 capacity build-out by Q2 2026
Company: WhiteFiber
What the later record shows
Delivered on time
A June 9, 2026 company presentation says Duke Energy had completed the work to deliver the initial 54 gross MW of utility power to NC-1, more than the 40 MW gross promised by end of Q2 2026. The exact energization date is not given.
“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Expects 24 MW energized in Q1 2026 and 16 MW more in Q2 2026 for total of 40 MW at NC-1 by end of Q2 2026
Source (primary)
WhiteFiber 424B4 filed 2025-08-08 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “Management expects another 24 MW (gross) will be energized in the first quarter of 2026 and that an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at the NC -1 site by the end of the second quarter of 2026.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus states the 24 MW and 16 MW energization expectations and the 40 MW total at NC-1 by the end of Q2 2026.
Confirmed in the source:
- Management expects 24 MW (gross) to be energized at NC-1 in Q1 2026
- Management expects an incremental 16 MW (gross) to be energized in Q2 2026
- This would bring NC-1 to a total of 40 MW (gross) by the end of Q2 2026
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025073279/ea0249945-07.htm) in full (825,843 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber 424B4 filed 2025-08-08
Quote: “Management expects another 24 MW (gross) will be energized in the first quarter of 2026 and that an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at the NC -1 site by the end of the second quarter of 2026.”
confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)
Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”