jain.com

MTL-3 site acquisition

Company: WhiteFiber

Subject kind
acquisition
Statement date
2025-07-22
Promised amount
7.0 MW
Event date
2025-04-11
Current status
stated

What the later record shows

Not a promise: a reported event · happened April 11, 2025

The claim reports the MTL-3 site rights as secured and announced on April 11, 2025. Later filings repeat this.

“On April 11, 2025 we announced that we had secured the rights to a new data center site in Saint -J érôme , Québec”
2025-08-07 · WhiteFiber 424B4 filed 2025-08-08 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Secured rights to new data center site in Saint-Jérôme, Québec for 7 MW (gross) Tier-3 data center (MTL-3), announced April 11, 2025

Source (primary)

WhiteFiber S-1/A filed 2025-07-23 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “On April 11, 2025 we announced that we had secured the rights to a new data center site in Saint-Jérôme, Québec, a suburb of Montreal ("MTL-3"), which will be a 7 MW (gross) Tier-3 data center.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The prospectus states that on April 11, 2025 the company announced it had secured rights to a Saint-Jérôme, Québec site that will be a 7 MW (gross) Tier-3 data center (MTL-3).

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025066839/ea0249945-s1a1_white.htm) in full (824,020 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber S-1/A filed 2025-07-23

Quote: “On April 11, 2025 we announced that we had secured the rights to a new data center site in Saint-Jérôme, Québec, a suburb of Montreal ("MTL-3"), which will be a 7 MW (gross) Tier-3 data center.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.