MTL-2 real estate acquisition
Company: WhiteFiber
What the later record shows
Not a promise: a reported event · happened December 27, 2024
The claim reports the MTL-2 real estate purchase as completed on December 27, 2024. Later filings confirm it.
“On December 27, 2024, we acquired the real estate and building for a build-to-suit 5 MW (gross) Tier-3 data center expansion project near Montreal, Canada”
2026-08-11 · WhiteFiber 10-Q filed 2026-08-12 View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Acquired real estate and building for 5 MW MTL-2 build-to-suit data center expansion in Montreal
Source (primary)
WhiteFiber 424B4 filed 2025-08-08 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “On December 27, 2024, we acquired the real estate and building for a build -to -suit 5 MW (gross) Tier -3 data center expansion project in Montreal ("MTL -2 ").”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus states this acquisition directly, including the date, the 5 MW capacity and the Montreal location.
Confirmed in the source:
- On December 27, 2024, WhiteFiber acquired the real estate and building for MTL-2
- MTL-2 is a build-to-suit 5 MW (gross) Tier-3 data center expansion project in Montreal
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025073279/ea0249945-07.htm) in full (825,843 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber 424B4 filed 2025-08-08
Quote: “On December 27, 2024, we acquired the real estate and building for a build -to -suit 5 MW (gross) Tier -3 data center expansion project in Montreal ("MTL -2 ").”