Enovum acquisition

Company: WhiteFiber

Subject kind
acquisition
Statement date
2025-08-07
Event date
2024-10-11
Current status
stated

What the later record shows

Not a promise: a reported event · happened October 11, 2024

The claim states a completed acquisition on October 11, 2024, including the MTL-1 lease. Later filings confirm both.

“We acquired Enovum on October 11, 2024. The transaction included the lease of MTL-1, our 4 MW (gross) Tier-3 high-performance computing”
2026-08-11 · WhiteFiber 10-Q filed 2026-08-12 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Acquired Enovum and 4 MW MTL-1 data center in Montreal

Source (primary)

WhiteFiber 424B4 filed 2025-08-08 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We acquired Enovum on October 11, 2024. The transaction included the lease to MTL -1 , a fully operational and fully leased to customers 4 MW (gross) Tier -3 datacenter headquartered in Montreal, Canada.”

How we checked this

Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.

The prospectus confirms the Enovum acquisition and that MTL-1 is a 4 MW Montreal data center. However, it says the deal included the lease to MTL-1, not ownership of the facility.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025073279/ea0249945-07.htm) in full (825,843 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber 424B4 filed 2025-08-08

Quote: “We acquired Enovum on October 11, 2024. The transaction included the lease to MTL -1 , a fully operational and fully leased to customers 4 MW (gross) Tier -3 datacenter headquartered in Montreal, Canada.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.