Capacity target by end of 2025

Company: WhiteFiber

Subject kind
guidance
Statement date
2025-08-07
Promised by
2025-12-31
Promised amount
16.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

A June 2026 investor deck shows about 11 MW gross online in 2025, short of the ~16 MW target. MTL-3 became operational in Q4 2025, but development of the 5 MW MTL-2 site was put on hold.

“MTL - 3 7 Gross MW Capacity: 100% Operational Customer: Cerebras Systems IT Load: 5 MW”
2026-01-25 · whitefiber 8-K exhibit (ea027401701ex99-1_white.htm) View cached copy (2026-09-21)Live source ↗
“MTL-2 5.0 MW(2) ~11 MW Online in 2025 ~76 MW Online by YE 2026E”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
“(2) Development of MTL-2 has been put on hold. (3) Pipeline defined as data center sites”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Expects to add 12 MW (gross) of capacity inclusive of MTL-2 and MTL-3 for total of approximately 16 MW (gross) by end of 2025

Source (primary)

WhiteFiber 424B4 filed 2025-08-08 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL -2 and MTL -3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The prospectus states this capacity expectation directly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025073279/ea0249945-07.htm) in full (825,843 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber 424B4 filed 2025-08-08

Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL -2 and MTL -3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.