2026 total data center capacity target

Company: WhiteFiber

Subject kind
guidance
Statement date
2026-03-25
Promised by
2026-12-31
Promised amount
76.0 MW
Current status
stated

The claim, verbatim

Intend to achieve estimated 76 MW (gross) of total data center capacity by end of Q4 2026

Source (primary)

WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We are aggressively pursuing our development pipeline and intend to achieve an estimated 76 MW (gross) of total data center capacity by the end of the fourth quarter of 2026”

How we checked this

Checked on September 15, 2026. The cited source supports every part of this claim.

The 10-K states this capacity target. It notes that MTL-2, MTL-3 and NC-1 underpin the target and that it is subject to change.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390026034341/ea0278305-10k_white.htm) in full (600,249 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber 10-K filed 2026-03-26

Quote: “We are aggressively pursuing our development pipeline and intend to achieve an estimated 76 MW (gross) of total data center capacity by the end of the fourth quarter of 2026”

View cached copy (2026-08-31)Live source ↗