stated

The claim, verbatim

Principal amortization will commence on a semi-annual basis only after completion of the Abernathy HPC Campus

Source (primary)

TeraWulf 8-K filed 2025-12-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “No amortization will be payable prior to the completion of the Abernathy HPC Campus.”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

The filing's amortization section states both the semi-annual schedule and the condition that no amortization is due before the campus is completed.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000110465925124839/tm2534384d1_8k.htm) in full (10,443 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf 8-K filed 2025-12-29

Quote: “No amortization will be payable prior to the completion of the Abernathy HPC Campus.”

View cached copy (2026-08-31)Live source ↗