Cayuga Phase 2
Company: TeraWulf - Project: Cayuga Site
The claim, verbatim
Cayuga Phase 2 will add 162 MW of capacity in 2028
Source (primary)
Q2 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗
Quote: “+162 MW (2028)”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
Cayuga's estimated buildout timeline lists +162 MW in 2028 as Phase II, bringing the total to 300 MW.
Confirmed in the source:
- Cayuga's estimated buildout includes a Phase II
- Phase II adds +162 MW
- Phase II is scheduled for 2028
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23302/pdf/WULF_Q2_2025_Investor_Update_%28Aug_2025%29vF.pdf) in full (17,599 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Q2 Earnings Update Presentation
Quote: “+162 MW (2028)”