Abernathy HPC datacenter joint venture
Company: TeraWulf - Project: Abernathy HPC Campus
What the later record shows
Not a promise: a reported event · happened October 27, 2025
The claim reports that the amended and restated LLC agreement was entered on October 27, 2025, which is a past event. Later filings restate the same date.
“Abernathy Joint Venture On October 27, 2025, the Company entered into an amended and restated limited liability company agreement governing the Abernathy Joint Venture.”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Entered amended and restated LLC agreement with Fluidstack to construct and operate 168 MW HPC datacenter campus in Abernathy, Texas
Source (primary)
View 10-K PDF (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “On October 27, 2025, the Company, through its subsidiary Big Country Wulf LLC (the "TeraWulf Member"), and Fluidstack CS I Inc. ("Fluidstack Member") entered into an amended and restated limited liability company agreement (the "Abernathy Joint Venture Agreement") to govern the terms of operation of FS CS I LLC (the "Abernathy Joint Venture"), which will construct and operate a 168 MW critical IT load datacenter campus in Abernathy, Texas (the "Abernathy HPC Campus").”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
Note 1 of the 10-K describes the amended and restated LLC agreement with the Fluidstack member and the 168 MW Abernathy campus the joint venture will build and operate.
Confirmed in the source:
- On October 27, 2025, TeraWulf, through a subsidiary, entered into an amended and restated LLC agreement with Fluidstack CS I Inc.
- The Abernathy Joint Venture will construct and operate a 168 MW critical IT load datacenter campus in Abernathy, Texas
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000031/0001083301-26-000031.pdf) in full (556,251 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms View 10-K PDF
Quote: “On October 27, 2025, the Company, through its subsidiary Big Country Wulf LLC (the "TeraWulf Member"), and Fluidstack CS I Inc. ("Fluidstack Member") entered into an amended and restated limited liability company agreement (the "Abernathy Joint Venture Agreement") to govern the terms of operation of FS CS I LLC (the "Abernathy Joint Venture"), which will construct and operate a 168 MW critical IT load datacenter campus in Abernathy, Texas (the "Abernathy HPC Campus").”