MicroBT miners delivery schedule
Company: Riot
What the later record shows
Outcome not yet confirmed
The latest passage (Q1 2026 10-Q, April 2026) only repeats the expectation that all MicroBT miners will be received by Q2 2026. No passage confirms receipt or a slip after the deadline.
“all miners under these purchase orders are expected to be received by the second quarter of 2026, with deployment continuing on an ongoing basis”
2026-04-29 · Riot 10-Q filed 2026-04-30 View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
All miners under current MicroBT purchase orders are expected to be received by second quarter of 2026, with deployment following on an ongoing basis
Source (primary)
Riot 10-K filed 2026-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “All miners under current purchase orders are expected to be received by the second quarter of 2026, with deployment following on an ongoing basis.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The 10-K says all miners under current MicroBT purchase orders are expected by Q2 2026, with deployment following on an ongoing basis.
Confirmed in the source:
- Riot has current purchase orders for miners from MicroBT under its Master Agreement
- All miners under the current purchase orders are expected to be received by the second quarter of 2026
- Deployment of the miners is to follow on an ongoing basis
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000110465926022322/riot-20251231x10k.htm) in full (516,452 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot 10-K filed 2026-03-02
Quote: “All miners under current purchase orders are expected to be received by the second quarter of 2026, with deployment following on an ongoing basis.”