jain.com

River Bend Data Center Project Capacity

Company: Hut 8 - Project: River Bend

Subject kind
facility capacity
Statement date
2026-04-30
Promised amount
245.0 MW
Current status
stated

The claim, verbatim

Hut 8 is developing and constructing a turnkey data center with 245 megawatts of critical IT capacity and related substation at its River Bend campus in St. Francisville, Louisiana

Source (primary)

Hut 8 8-K filed 2026-05-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “finance a portion of the development and construction of a turnkey data center with 245 megawatts of critical IT capacity and the related substation at the Company's River Bend campus located in St. Francisville, Louisiana (collectively, the "Data Center Project")”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Hut 8 8-K filed 2026-05-01

Quote: “finance a portion of the development and construction of a turnkey data center with 245 megawatts of critical IT capacity and the related substation at the Company's River Bend campus located in St. Francisville, Louisiana (collectively, the "Data Center Project")”

View cached copy (2026-08-30)Live source ↗