jain.com

River Bend data center 245 MW capacity leased

Company: Hut 8 - Project: River Bend

Subject kind
facility capacity
Statement date
2025-12-16
Promised amount
245.0 MW
Current status
stated

The claim, verbatim

245 megawatts of IT capacity at River Bend data center campus leased to Fluidstack

Source (primary)

Hut 8 8-K filed 2025-12-17 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “245 megawatts of IT capacity at the Company's River Bend data center campus in Louisiana”

How we checked this

Attempted on September 16, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1964789/000110465925122052/hut-20251217x8k.htm) in full (3,550 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Hut 8 8-K filed 2025-12-17

Quote: “245 megawatts of IT capacity at the Company's River Bend data center campus in Louisiana”

View cached copy (2026-08-31)Live source ↗