River Bend data center 245 MW capacity leased
Company: Hut 8 - Project: River Bend
The claim, verbatim
245 megawatts of IT capacity at River Bend data center campus leased to Fluidstack
Source (primary)
Hut 8 8-K filed 2025-12-17 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “245 megawatts of IT capacity at the Company's River Bend data center campus in Louisiana”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Hut 8 8-K filed 2025-12-17
Quote: “245 megawatts of IT capacity at the Company's River Bend data center campus in Louisiana”
