jain.com

Senior Notes interest payments

Company: CoreWeave

Subject kind
financing
Statement date
2025-07-27
Promised by
2026-02-01
Promised amount
9.0 percent
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

Later filings only restate that interest is payable semi-annually beginning February 1, 2026. No passage confirms that the February 1, 2026 interest payment was actually made.

“bear interest at a rate of 9.00% per annum, payable semi-annually in cash in arrears on February 1 and August 1, of each year beginning on February 1, 2026”
2025-11-12 · CoreWeave 10-Q filed 2025-11-13 View cached copy (2026-08-31)Live source ↗

Checked October 11, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Notes bear interest at 9.000% per annum, payable semi-annually on February 1 and August 1 each year, beginning February 1, 2026

Source (primary)

CoreWeave 8-K filed 2025-07-28 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “bear interest at a rate of 9.000% per annum, payable semi-annually in cash in arrears on February 1 and August 1 of each year, beginning on February 1, 2026”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

CoreWeave's 8-K states the 9.000% Senior Notes due 2031 bear interest at 9.000% per annum, payable semi-annually on February 1 and August 1, beginning February 1, 2026, which matches every part of the claim.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1769628/000119312525165924/d73657d8k.htm) in full (7,431 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CoreWeave 8-K filed 2025-07-28

Quote: “bear interest at a rate of 9.000% per annum, payable semi-annually in cash in arrears on February 1 and August 1 of each year, beginning on February 1, 2026”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.