Data center power capacity expansion to year-end 2026

Company: CoreWeave

Subject kind
facility capacity
Statement date
2026-09-01
Promised by
2026-12-31
Promised amount
1850.0 MW
Current status
stated

The claim, verbatim

Active power will scale from 1.5 gigawatts to more than 1.85 gigawatts by year-end 2026

Source (primary)

CoreWeave Offers So Much at $85 - Yahoo Finance (-, news_article)
View cached copy (2026-09-02)Live source ↗Archive.org ↗

Quote: “active power scaling from 1.5 gigawatts today toward more than 1.85 gigawatts by year end”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CoreWeave Offers So Much at $85 - Yahoo Finance

Quote: “active power scaling from 1.5 gigawatts today toward more than 1.85 gigawatts by year end”

View cached copy (2026-09-02)Live source ↗Archive.org ↗