Total contracted capacity across five sites

Company: Core Scientific

Subject kind
customer
Statement date
2026-03-30
Promised amount
590.0 MW
Current status
stated

The claim, verbatim

Total contracted capacity is approximately 590 megawatts across five data center sites

Source (primary)

Core Scientific DEF 14A filed 2026-03-31 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “bringing total contracted capacity to approximately 590 megawatts across five data center sites”

How we checked this

Checked on September 15, 2026. The cited source supports every part of this claim.

The CEO's letter says the expansion brought total contracted capacity to approximately 590 megawatts across five data center sites.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1839341/000119312526134857/d119389ddef14a.htm) in full (264,939 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Core Scientific DEF 14A filed 2026-03-31

Quote: “bringing total contracted capacity to approximately 590 megawatts across five data center sites”

View cached copy (2026-08-31)Live source ↗