This claim was marked delayed on September 3, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
guidance
Statement date
2026-09-01
Promised by
2025-12-31
Current status
delayed

The claim, verbatim

Expected one or more new power contracts at existing sites by Q4 2025

Source (primary)

Investor Conference Call Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “One or more new power contract(s) at existing site(s)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Investor Conference Call Presentation

Quote: “One or more new power contract(s) at existing site(s)”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed