jain.com

Hunt County ERCOT interconnection approval

Company: Core Scientific

Subject kind
regulatory
Statement date
2026-09-01
Current status
stated

The claim, verbatim

Power and ramp schedule for Hunt County site approved through ERCOT interconnection process in October 2024

Source (primary)

Fourth Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Power and ramp schedule approved through ERCOT interconnection process in October 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Fourth Quarter Fiscal Year 2025 Earnings Presentation

Quote: “Power and ramp schedule approved through ERCOT interconnection process in October 2024”

View cached copy (2026-09-01)Live source ↗Archive.org ↗