Hunt County ERCOT interconnection approval
Company: Core Scientific
The claim, verbatim
Power and ramp schedule for Hunt County site approved through ERCOT interconnection process in October 2024
Source (primary)
Fourth Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “Power and ramp schedule approved through ERCOT interconnection process in October 2024”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The Hunt County site details slide states this ERCOT approval and its date.
Confirmed in the source:
- The Hunt County site's power and ramp schedule was approved through the ERCOT interconnection process in October 2024
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11266/pdf/Q4+FY25+earnings+deck+vfinal.2+PDF.pdf) in full (13,731 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Fourth Quarter Fiscal Year 2025 Earnings Presentation
Quote: “Power and ramp schedule approved through ERCOT interconnection process in October 2024”