HPC infrastructure allocation plan
Company: Core Scientific
The claim, verbatim
Plan to allocate 700 megawatts for HPC: 500 MW for hosted GPUs, 200 MW for HPC support infrastructure; remaining 500 MW for bitcoin mining
Source (primary)
Core Scientific, Inc. Investor and Analyst Event June 12, 2024 Transcript (IR page (investors.corescientific.com), earnings_call)
View cached copy (2026-09-01)Live source ↗
Quote: “we aim to provide 700 megawatts for HPC, of which 500 megawatts will be for the hosted GPUs, so that's about 200 megawatts that are needed in order to support those facilities. This leaves about 500 megawatts of our existing portfolio for bitcoin mining.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Core Scientific, Inc. Investor and Analyst Event June 12, 2024 Transcript
Quote: “we aim to provide 700 megawatts for HPC, of which 500 megawatts will be for the hosted GPUs, so that's about 200 megawatts that are needed in order to support those facilities. This leaves about 500 megawatts of our existing portfolio for bitcoin mining.”