CoreWeave cumulative HPC infrastructure delivery - 2H 2025
Company: Core Scientific
What the later record shows
Delivered; the record does not say when
By March 2, 2026, ~350 MW was energized for CoreWeave, more than 270 MW. However, on October 30, 2025 the company targeted only 250 MW by end-2025 and had ~120+ MW energized, so 270 MW may not have been reached in 2H 2025.
“CoreWeave construction progress Denton Marble ~120+ MW Energized Across Denton & Marble Sites Precast Building Completed at Dalton 1 & Muskogee Sites”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“Continued Execution on CoreWeave Contract: To date, energized ~350 MW of power and remain on track to deliver ~590 MW by early 2027.”
2026-03-01 · core-scientific 8-K exhibit (q42025corescientificinc-ea.htm) View cached copy (2026-09-13)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cumulative 270 MW of HPC infrastructure delivery to CoreWeave by 2H 2025
Source (primary)
Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗
Quote: “270MW 2H 2025”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The same timeline on the CoreWeave transaction summary slide lists 270 MW cumulative for 2H 2025. This is a planned schedule as of November 6, 2024, not a report of completed delivery.
Confirmed in the source:
- Core Scientific's CoreWeave transaction summary shows a cumulative HPC infrastructure delivery of 270 MW for 2H 2025
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Third Quarter Fiscal Year 2024 Earnings Presentation
Quote: “270MW 2H 2025”
confirms Investor Conference Call Presentation
Quote: “CoreWeave construction progress Denton Marble ~120+ MW Energized Across Denton & Marble Sites Precast Building Completed at Dalton 1 & Muskogee Sites”
confirms core-scientific 8-K exhibit (q42025corescientificinc-ea.htm)
Quote: “Continued Execution on CoreWeave Contract: To date, energized ~350 MW of power and remain on track to deliver ~590 MW by early 2027.”