CoreWeave cumulative HPC infrastructure delivery - 2H 2025

Company: Core Scientific

Subject kind
facility timeline
Statement date
2024-11-06
Promised by
2025-12-31
Promised amount
270.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

By March 2, 2026, ~350 MW was energized for CoreWeave, more than 270 MW. However, on October 30, 2025 the company targeted only 250 MW by end-2025 and had ~120+ MW energized, so 270 MW may not have been reached in 2H 2025.

“CoreWeave construction progress Denton Marble ~120+ MW Energized Across Denton & Marble Sites Precast Building Completed at Dalton 1 & Muskogee Sites”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“Continued Execution on CoreWeave Contract: To date, energized ~350 MW of power and remain on track to deliver ~590 MW by early 2027.”
2026-03-01 · core-scientific 8-K exhibit (q42025corescientificinc-ea.htm) View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Cumulative 270 MW of HPC infrastructure delivery to CoreWeave by 2H 2025

Source (primary)

Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗

Quote: “270MW 2H 2025”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The same timeline on the CoreWeave transaction summary slide lists 270 MW cumulative for 2H 2025. This is a planned schedule as of November 6, 2024, not a report of completed delivery.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Third Quarter Fiscal Year 2024 Earnings Presentation

Quote: “270MW 2H 2025”

View cached copy (2026-09-01)Live source ↗

confirms Investor Conference Call Presentation

Quote: “CoreWeave construction progress Denton Marble ~120+ MW Energized Across Denton & Marble Sites Precast Building Completed at Dalton 1 & Muskogee Sites”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms core-scientific 8-K exhibit (q42025corescientificinc-ea.htm)

Quote: “Continued Execution on CoreWeave Contract: To date, energized ~350 MW of power and remain on track to deliver ~590 MW by early 2027.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2024-11-06.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.