CoreWeave cumulative HPC infrastructure delivery - 1H 2025
Company: Core Scientific
What the later record shows
The date slipped · new target December 31, 2025
The May 2025 plan shows about 65 MW delivered by end of Q2 2025, not 200 MW. The company now targets 250 MW by the end of 2025.
“On track to deliver 250 MW by the end of 2025”
2025-05-07 · First Quarter Fiscal Year 2025 Earnings Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“Expect to deliver 8 MW of billable capacity at Denton this month and an additional 40 MW by the end of the second quarter”
2025-05-07 · First Quarter Fiscal Year 2025 Earnings Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cumulative 200 MW of HPC infrastructure delivery to CoreWeave by 1H 2025
Source (primary)
Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗
Quote: “200MW 1H 2025”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The CoreWeave transaction summary slide lists a cumulative infrastructure delivery timeline of 200 MW in 1H 2025. This is a planned schedule as of November 6, 2024, not a report of completed delivery.
Confirmed in the source:
- Core Scientific's CoreWeave transaction summary shows a cumulative HPC infrastructure delivery of 200 MW for 1H 2025
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Third Quarter Fiscal Year 2024 Earnings Presentation
Quote: “200MW 1H 2025”
delays First Quarter Fiscal Year 2025 Earnings Presentation
Quote: “On track to deliver 250 MW by the end of 2025”