CoreWeave cumulative HPC infrastructure delivery - 1H 2026
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
The latest delivery passage (May 2025) only forecasts 250 MW by end-2025 and ~590 MW by early 2027. No passage reports how many MW had actually been delivered to CoreWeave by mid-2026.
“On track to deliver 250 MW by the end of 2025”
2025-05-07 · First Quarter Fiscal Year 2025 Earnings Presentation View cached copy (2026-09-26)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cumulative 382 MW of HPC infrastructure delivery to CoreWeave by 1H 2026
Source (primary)
Third Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗
Quote: “382MW 1H 2026”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The CoreWeave cumulative infrastructure delivery timeline shows 382 MW in 1H 2026.
Confirmed in the source:
- Cumulative HPC infrastructure delivery to CoreWeave is scheduled at 382 MW by 1H 2026
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11130/pdf/Core%2BScientific%2BQ3%2B2024%2BEarnings%2BPresentation.pdf) in full (24,743 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Third Quarter Fiscal Year 2024 Earnings Presentation
Quote: “382MW 1H 2026”