Promised amount
2.0 GW
Current status
stated

The claim, verbatim

AMD has exclusive rights to reserve up to an additional 2 GW of future capacity

Source (primary)

Core Scientific Doubles AI Capacity to 1.1 GW in $14B AMD Deal (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “gives AMD exclusive rights to reserve up to an additional 2 GW of future capacity”

How we checked this

Attempted on September 14, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://www.datacenterknowledge.com/deals/core-scientific-doubles-ai-capacity-to-1-1-gw-in-14b-amd-deal) in full (12,524 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Core Scientific Doubles AI Capacity to 1.1 GW in $14B AMD Deal

Quote: “gives AMD exclusive rights to reserve up to an additional 2 GW of future capacity”

View cached copy (2026-08-31)Live source ↗