jain.com

AMD expansion capex requirement

Company: Core Scientific

Subject kind
financing
Statement date
2026-07-28
Promised amount
104.0 USD millions
Current status
stated

The claim, verbatim

Core Scientific responsible for funding $104 Million of capex for the additional 70 MW AMD expansion

Source (primary)

Second Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “For the additional 70 MW expansion, Core Scientific is responsible for funding $104 Million of capex”

How we checked this

Checked on October 10, 2026. The cited source supports part of this claim, but not all of it.

The deck states Core Scientific must fund $104M of capex for an additional 70 MW expansion, but this appears in a footnote to the CoreWeave contract summary, not in connection with AMD.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11282/pdf/Q2+FY26+earnings+deck+7.28+AM.pdf) in full (12,585 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Second Quarter Fiscal Year 2026 Earnings Presentation

Quote: “For the additional 70 MW expansion, Core Scientific is responsible for funding $104 Million of capex”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2026-07-28.