jain.com

Sandersville, Georgia data center capacity under lease

Company: CleanSpark - Project: Sandersville

Subject kind
facility capacity
Statement date
2026-07-13
Promised amount
175.0 MW
Current status
stated

The claim, verbatim

Tenant will lease data center infrastructure at Sandersville, Georgia campus supporting 175 megawatts of critical information technology load

Source (primary)

CleanSpark 8-K filed 2026-07-14 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “Under the Lease, the Tenant will lease data center infrastructure at the Company's Sandersville, Georgia campus supporting 175 megawatts of critical information technology load.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark 8-K filed 2026-07-14

Quote: “Under the Lease, the Tenant will lease data center infrastructure at the Company's Sandersville, Georgia campus supporting 175 megawatts of critical information technology load.”

View cached copy (2026-08-30)Live source ↗