Sandersville bitcoin mining decommissioning timeline
Company: CleanSpark - Project: Sandersville
The claim, verbatim
Expects to fully decommission existing bitcoin mining operations at Sandersville, Georgia during fiscal year 2028 to transition capacity to data center use
Source (primary)
CleanSpark 10-Q filed 2026-08-06 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗
Quote: “Following the execution of the Sandersville Lease, management began planning the transition of the power capacity currently supporting bitcoin mining operations at the site exclusively to data center use and expects to fully decommission the existing bitcoin mining operations at the site during fiscal year 2028.”
How we checked this
Checked on September 2, 2026. The cited source supports every part of this claim.
The 10-Q states both the fiscal 2028 decommissioning expectation and the planned shift of that power capacity to data center use.
Confirmed in the source:
- CleanSpark expects to fully decommission existing bitcoin mining operations at the Sandersville site during fiscal year 2028
- Management is planning to transition the site's power capacity currently supporting bitcoin mining exclusively to data center use
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000119312526338382/clsk-20260630.htm) in full (222,344 characters, retrieved August 30, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark 10-Q filed 2026-08-06
Quote: “Following the execution of the Sandersville Lease, management began planning the transition of the power capacity currently supporting bitcoin mining operations at the site exclusively to data center use and expects to fully decommission the existing bitcoin mining operations at the site during fiscal year 2028.”