Three datacenters 500MW operating by H1 2023

Company: Applied Digital

Subject kind
guidance
Statement date
2022-08-25
Promised by
2023-06-30
Promised amount
500.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

Jamestown (106 MW) and Ellendale (180 MW) exist as hosting facilities. Ellendale reached full capacity only around August 2024 after transformer issues. The 200 MW Garden City, TX campus was sold to Marathon on April 1, 2024, so the full ~500 MW across three sites was not delivered by H1 2023.

“The Company successfully procured new transformers and related components from North American manufacturers resulting in the Company's Ellendale Data Center Hosting facility to operate at full capacity as of the date of this earnings release”
2024-08-28 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company also broke ground on a 100 MW HPC data center in project in Ellendale, ND, on land located adjacent to its existing 180 MW Data center hosting facility.”
2024-10-21 · ARS View cached copy (2026-09-01)Live source ↗Archive.org ↗
“We completed the sale transaction on April 1, 2024.”
2024-10-22 · Applied Digital S-1 filed 2024-10-23 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company expects to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity, already fully committed through contract or option

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “We expect to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity, which is already fully committed through contract or option.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

CEO Wes Cummins is quoted stating each element of this expectation.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/37/applied-blockchain-reports-fiscal-fourth-quarter-and-full/) in full (21,726 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “We expect to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity, which is already fully committed through contract or option.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “We expect to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity, which is already fully committed through contract or option.”

View cached copy (2026-09-25)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “We expect to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity, which is already fully committed through contract or option.”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “We expect to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity, which is already fully committed through contract or option.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “We expect to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “We expect to have three datacenters operating by the first half of calendar 2023, representing nearly 500 megawatts of total hosting capacity, which is already fully committed through contract or option.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2022-08-25.