Texas wind farm facility operational timing
Company: Applied Digital
What the later record shows
The date slipped · new target December 31, 2023
The Garden City, Texas 200MW facility was not operating by end of 2022. Its expected start moved to Q1 2023, then to the second half of 2023. The 2025 annual report lists only North Dakota sites as operating.
“The facility is nearing completion and is expected to begin operating in the first calendar quarter of 2023.”
2023-01-09 · Applied Digital 10-Q filed 2023-01-10 View cached copy (2026-09-13)Live source ↗
“The facility is expected to begin operating in the second half of calendar 2023 and the 200 MW capacity is fully contracted with our customers.”
2023-08-01 · Applied Digital 10-K filed 2023-08-02 View cached copy (2026-09-13)Live source ↗
“We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW”
2025-09-20 · ARS View cached copy (2026-09-01)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
200MW Texas wind farm expected to be operational in latter half of calendar 2022
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “On November 24, 2021, Applied Blockchain entered into a letter of intent to develop a facility in Texas with 200MW of wind power. Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The May 2022 release says construction of the 200MW Texas wind facility began in April 2022 and it is expected to be operational in the latter half of the calendar year, which is 2022.
Confirmed in the source:
- The Texas facility has 200MW of wind power
- The facility is expected to be operational in the latter half of calendar 2022
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,855 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “On November 24, 2021, Applied Blockchain entered into a letter of intent to develop a facility in Texas with 200MW of wind power. Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year.”
delays ARS
Quote: “We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW”
delays Applied Digital 10-K filed 2023-08-02
Quote: “The facility is expected to begin operating in the second half of calendar 2023 and the 200 MW capacity is fully contracted with our customers.”
delays Applied Digital 10-Q filed 2023-01-10
Quote: “The facility is nearing completion and is expected to begin operating in the first calendar quarter of 2023.”