The claim, verbatim
Polaris Forge 1 comprises three data centers purpose-built for high power density GPUs to support HPC and AI applications
Source (primary)
ARS (IR page (ir.applieddigital.com), ir_release)
View cached copy (2026-09-01)Live source ↗
Quote: “These facilities are purpose built for high power density GPUs and along with a third 150 MW data center, will comprise our Polaris Forge 1 campus.”
How we checked this
Checked on October 10, 2026. The cited source supports part of this claim, but not all of it.
The 10-K describes all three buildings as an AI- and HPC-focused campus. However, its 'purpose built for high power density GPUs' wording refers only to the first two buildings under construction, not the third.
Confirmed in the source:
- Polaris Forge 1 is planned to comprise three data centers in Ellendale, North Dakota
- The three data centers are described as HPC-focused and AI-focused facilities
- The first two buildings (100 MW and 150 MW) are purpose-built for high power density GPUs
We could not confirm this from the cited source:
- The 10-K does not explicitly state that the third 150 MW Polaris Forge 1 data center is purpose-built for high power density GPUs
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001493152-25-014502/formars.pdf) in full (529,223 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms ARS
Quote: “These facilities are purpose built for high power density GPUs and along with a third 150 MW data center, will comprise our Polaris Forge 1 campus.”