Multiple facility sites construction start
Company: Applied Digital
What the later record shows
Partly delivered
Of the up-to-three sites totalling over 600MW, the passages show only the Ellendale, North Dakota 180MW facility being built. Its energizing began March 4, 2023.
“Applied Digital’s third co-hosting facility is in Ellendale, North Dakota with planned capacity of 180MW.”
2023-01-09 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company took possession of the land on August 15, 2022, built a hosting facility, and began energizing the site on March 4, 2023.”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Up to three sites in other states with total combined capacity over 600MW expected to be in construction before end of calendar 2022
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “In addition to the Texas sites, Applied Blockchain plans to be in construction on up to three other sites in three other states, including North Dakota, with total combined capacity of over 600MW before the end of calendar 2022.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release states that the company plans to be in construction on up to three sites in three other states, totaling over 600MW, before the end of calendar 2022.
Confirmed in the source:
- Applied Blockchain plans construction on up to three other sites in other states
- The sites have total combined capacity of over 600MW
- Construction is planned before the end of calendar 2022
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,855 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “In addition to the Texas sites, Applied Blockchain plans to be in construction on up to three other sites in three other states, including North Dakota, with total combined capacity of over 600MW before the end of calendar 2022.”